AAUC Allied Gold Corporation Material – Positive: Allied Delivers Sadiola Phase 1 on Schedule but High Operating Costs and Geopolitical Volatility Temper the Expansion Milestone

News Summary

The news release dated December 21, 2025, confirms that Allied Gold has commenced ore processing at the Sadiola Phase 1 expansion in Mali. The project was delivered on schedule (Q4 2025) and involves a new comminution circuit allowing the plant to treat up to 60% fresh ore at a rate of 5.7 Mtpa. Additionally, the company provided a production update for Q4 2025, expecting 113,000 ounces (60,000 from Sadiola), which puts the company on track to meet its full-year 2025 guidance of 375,000 ounces. Studies for a capital-efficient “Modular” Phase 2 expansion at Sadiola are nearing completion, with an update expected in early 2026.

Material Impact

Operational Milestone: Delivering the Sadiola Phase 1 expansion on schedule is a significant validation of management’s ability to execute in a difficult jurisdiction (Mali). The transition to processing more fresh ore is critical for sustaining production levels as oxide resources deplete.
Production Confirmation: The Q4 2025 production estimate of 113,000 ounces is a 30% increase over Q3 (87,020 oz), though it sits at the lower end of the 118,000-122,000 range suggested in the October 2025 investor presentation.
Guidance vs. Reality: While the company is meeting its 2025 annual guidance, the AISC remains high ($2,092 in Q3 2025). The Phase 1 expansion is expected to lower unit costs, but the true impact will not be visible until the Q1 2026 reporting cycle.
Strategic Shift: The mention of a “Modular Phase 2” suggests a shift toward capital efficiency (likely lower upfront Capex) compared to the original $400 million feasibility study plant. This indicates a more conservative approach to capital allocation.

Catalysts

Phase 2 Expansion Study (Early 2026): Details on the “Modular” approach will determine the capital intensity and debt requirements for the next three years.
Kurmuk Progress Update: First gold at the Ethiopian project is targeted for mid-2026; any logistical delays in the next 6 months would be severely negative.
Mali Political Stability: Despite management’s “business as usual” rhetoric in transcripts, fuel supply disruptions and potential changes in the Malian mining code remain systemic risks.
2025 Reserve and Resource Update (February 2026): Crucial for verifying mine life extensions at Agbaou and the impact of Oume on Bonikro.

Materiality Conclusion

The news is Material – Positive as it marks the successful completion of a major growth project on time. This de-risks the Sadiola production profile for 2026. However, it is not a “Game Changer” because the high AISC and geopolitical overhang still require the company to prove it can translate higher production into significant free cash flow.