GMIN G Mining Ventures Corp. Material – Positive: G Mining Secures Final Permit for Flagship Oko West Project, Clearing Path to Become Intermediate Producer

News Summary

On December 8, 2025, G Mining Ventures announced it has been granted a 20-year Mining License for its 100%-owned Oko West Gold Project in Guyana. This license, effective December 5, 2025, represents the final major permitting milestone required for the project. It formally authorizes the company to proceed with the full development, operation, and commercial production of gold. With this approval, the company plans to begin pre-production open-pit mining in the first quarter of 2026. The CEO, Louis-Pierre Gignac, emphasized the strong collaborative relationship with Guyanese authorities and the company’s commitment to responsible development.

Material Impact

The receipt of the Mining License is a material and positive de-risking event. While the market likely anticipated this successful outcome given the company’s steady progress, this official confirmation removes the final major uncertainty regarding the development of the Oko West project.

Looking at the progression of news in 2025, G Mining has systematically executed its strategy:
October 2: Secured a major tax reduction for its producing Tocantinzinho (TZ) mine, significantly boosting the cash flow intended to fund Oko West.
October 6: Secured a US$387.5 million non-dilutive financing package, removing funding risk for Oko West construction.
October 23: Made the formal construction decision for Oko West, officially launching the project.
November 12: Reported a stellar Q3 with record production and free cash flow from TZ, demonstrating the mine’s capacity to act as a funding engine.
December 8: Received the final Mining License, clearing the last regulatory hurdle.

This sequence demonstrates flawless execution by management. The license solidifies the project timeline, with pre-production mining now scheduled for Q1 2026. This transforms Oko West from a permitted development project into a mine-in-construction, shifting the primary risk from permitting to execution. Given the management team’s track record of delivering the TZ project on time and on budget, investor confidence in their ability to execute should be high. This news confirms the company is on a clear and unobstructed path to becoming a significant intermediate gold producer.

Catalysts

Q4 and Full-Year 2025 Results: Confirmation that the Tocantinzinho mine continues its strong operational performance and meets or exceeds the 2025 guidance of 175,000-200,000 oz at an AISC of $1,025-$1,155/oz. The Q1 2025 transcript noted SAG mill liner issues were resolved in April, and Q3 results were exceptionally strong; continued strength is expected.
Oko West Construction Updates: Progress reports on construction activities. The company guided for $200-$240 million in project capital spending for Oko West in 2025. Investors should monitor progress against the schedule and budget.
Commencement of Pre-Production Mining: News confirming the start of open-pit mining at Oko West in Q1 2026 will be a key operational milestone, demonstrating the project remains on track for first gold in H2 2027.
Gurupi Project Updates: Any news regarding the restart of exploration activities at the Gurupi project in Brazil following the favorable court ruling mentioned in the Q3 results.

Materiality Conclusion

The news is Material – Positive. It is the final government approval needed to build the company’s transformative growth asset. By eliminating the key jurisdictional and permitting risk for Oko West, it solidifies the company’s growth trajectory and allows management to focus entirely on construction and execution.