CBR Cabral Gold Inc. Material – Positive: Cabral Gold Shifts From Explorer to Builder With Cuiu Cuiu Fully Funded and On Schedule

News Summary

On December 17, 2025, Cabral Gold provided two updates. The primary release was a construction update on its Phase 1 gold-in-oxide heap leach project at the Cuiú Cuiú Gold District in Brazil. The company confirmed that the project remains on track and on budget for commercial production in Q4 2026. Key progress metrics reported include:
– Detailed engineering is 26% complete.
– Procurement of capital items is 65% complete by value.
– Earthworks for the processing plant and heap leach pads are 20% complete.
– There are 143 employees and contractors currently on site.
– The company reiterated its timeline, targeting plant construction in Q2 2026, commissioning in Q3 2026, and commercial production in Q4 2026.

In a separate release, the company announced it has upgraded its U.S. listing from the OTCQB Venture Market to the OTCQX Best Market, effective immediately. This is intended to provide greater visibility and liquidity for U.S. investors.

Material Impact

The construction update is materially positive. After the company’s transformative US$45.1 million gold loan financing announced in October and closed in November 2025, the primary risk for Cabral shifted from financing to execution. This news release is the first major progress report since construction officially commenced and it directly addresses execution risk.

By confirming that the project is proceeding on schedule and on budget, management is demonstrating its ability to deliver on its stated plans. The specific completion percentages for engineering, procurement, and earthworks provide tangible evidence of progress, moving the project from a plan on paper to a physical reality. This is precisely the kind of update the market needs to see to maintain confidence after the significant stock price appreciation that followed the financing news. While not a “game-changing” catalyst in itself, it is a crucial and positive de-risking event that reinforces the investment thesis.

The upgrade to the OTCQX is a routine, positive development. While beneficial for marketing and potentially improving trading liquidity for U.S. investors over the long term, it has minimal immediate impact on the company’s fundamental value. The main driver of the positive rating is the successful execution update.

Looking at the historical context, Cabral has systematically de-risked the Cuiú Cuiú project over the past year.
Early 2025: Focused on high-grade exploration results to build market interest.
Mid-2025: Delivered a significantly improved Pre-Feasibility Study (PFS) in July, which established a robust economic case for the starter project (78% IRR, US$74M NPV5 at $2,500/oz gold).
Late 2025: Secured full construction funding via a non-dilutive (at issuance) gold loan, removing the largest hurdle and triggering a major re-rating of the stock.

The current phase is all about building the mine. This news confirms the first steps are being taken successfully, keeping the company on its stated path to becoming a gold producer by late 2026.

Catalysts

Continued Construction Updates: Monitor subsequent progress reports for any deviation from the budget or schedule. Key milestones include the start of permanent camp construction (Jan 2026) and the commencement of plant construction (Q2 2026).
Infill Drilling Results: The company plans an infill drilling program at the MG pit in Q1 2026. Positive results could further de-risk the mine plan and confirm ore grades.
Exploration Drilling: While the focus is on construction, the company has stated it will continue exploration drilling. Results from targets like Mutum, Jerimum Cima, or Machichie NE could add to the long-term resource potential and provide supplementary catalysts.
Cash Burn Rate: With construction activities ramping up, the quarterly cash burn will increase significantly from the C$2.9 million reported in the quarter ending March 31, 2025. The next financial statements will be important to assess the adequacy of the current treasury (C$66M post-financing) to reach production.

Materiality Conclusion

The construction update is material and positive. It confirms the company is successfully executing on its plan to build the Cuiú Cuiú starter mine, directly mitigating the primary execution risk that investors are now focused on post-financing. This confirmation of on-time, on-budget progress is critical for sustaining market confidence and supporting the stock’s recent re-rating.